VIKRAM DEVELOPERS AND PROMOTERS

4 registered projects on our index, 4 still within it.

Counted from the MahaRERA public register — not from the builder's own past-experience declaration. Earliest registration here is from 2020. Covers Pune — the districts indexed so far, so a builder active elsewhere may have more.

4

Under construction

0

Completed with OC

0

Past declared date

0

Lapsed or flagged

No delivery record yet

None of their 4 projects has reached its declared possession date, so the register has nothing to show yet about how they deliver. The soonest is due Sept 2027.

Declared possession dates that moved

3 of 4 projects have a possession date different from the one first registered. Among those still to be handed over, the largest change is 1 year, on MIDORI TOWER PHASE 2. The middle one moved by 1 year.

Size of the portfolio

463 homes across the projects indexed here, where unit counts are on record.

Have they kept to the dates they registered?

Across 4 projects still waiting to be handed over.

1
Date never pushed back
3
Pushed back up to a year
0
Pushed back over a year

MahaRERA publishes the date a promoter declared, not the date an occupancy certificate was issued — so this measures revisions to their own commitment, which is what the register can show. Projects that have received their occupancy certificate are left out: a registration's completion date can be extended after part-occupancy, so a revision on a delivered project tells you nothing about when it was actually handed over.

Projects on the register (4)

Showing 4 of 4 registered

SortPossession dateProject nameSafety score

  • MIDORI TOWER PHASE 2

    VIKRAM DEVELOPERS AND PROMOTERS · Pune 411027

    P52100025516

    Due Sept 2027Date moved from Sept 2026

    Safety score

    Check it free →
  • MIDORI TOWER PHASE 3

    VIKRAM DEVELOPERS AND PROMOTERS · Pune 411027

    P52100025886

    Due Sept 2027Date moved from Sept 2026

    Safety score

    Check it free →
  • MIDORI TOWER PHASE 4

    VIKRAM DEVELOPERS AND PROMOTERS · Pune 411027

    P52100047339

    Due Sept 2027Date moved from Mar 2027

    Safety score

    Check it free →
  • MIDORI TOWER PHASE 5

    VIKRAM DEVELOPERS AND PROMOTERS · Pune 411027

    P52100052802

    Due Dec 2027

    Safety score

    Check it free →

Looking at one of these?

A builder's record is context, not a verdict on the flat you're buying. Run the safety check on the specific project before you pay anything.

Check a project free

Compiled from the MahaRERA public register. These are counts of the promoter's own legally-required disclosures — we describe the record, not the company. Possession dates are what the promoter declared, not a guarantee. Verify on maharera.maharashtra.gov.in.

Developers often register each project under a separate company, so one group may appear here under more than one name, and this page shows only the projects registered under “VIKRAM DEVELOPERS AND PROMOTERS”. How we compile this · Report a correction

Check a project