10 registered projects on our index, 3 completed with occupancy, 4 past the declared possession date, 3 still within it.

Counted from the MahaRERA public register — not from the builder's own past-experience declaration. Earliest registration here is from 2017. Covers Thane — the districts indexed so far, so a builder active elsewhere may have more.

3

Under construction

3

Listed complete

4

Past declared date

4

Lapsed or flagged

Of the projects whose date has arrived

3 of 7 have completion recorded on MahaRERA. 4 are past the declared date with no completion on record.

Declared possession dates that moved

6 of 10 projects have a possession date different from the one first registered. Among those still to be handed over, the largest change is 8 years, on GAURAV ASTER. The middle one moved by 3 years 5 months.

Registration status

4 registrations have lapsed

Size of the portfolio

979 homes across the projects indexed here, where unit counts are on record.

Have they kept to the dates they registered?

Across 7 projects still waiting to be handed over.

1
Date never pushed back
1
Pushed back up to a year
5
Pushed back over a year

MahaRERA publishes the date a promoter declared, not the date an occupancy certificate was issued — so this measures revisions to their own commitment, which is what the register can show. Projects that have received their occupancy certificate are left out: a registration's completion date can be extended after part-occupancy, so a revision on a delivered project tells you nothing about when it was actually handed over.

Projects on the register (10)

  • GAURAV ASTER

    Ravi Developments · Thane 401107

    P51700011796

    Due Dec 2026Date moved from Dec 2018

    Safety score

    Check it free →
  • Gaurav Excellency

    Ravi Developments · Thane 400107

    P51700006232

    Due Mar 2027Date moved from Dec 2023

    Safety score

    Check it free →
  • GAURAV ENCLAVE

    Ravi Developments · Thane 401107

    P51700007276

    Due Dec 2028Date moved from Dec 2022

    Safety score

    Check it free →

Looking at one of these?

A builder's record is context, not a verdict on the flat you're buying. Run the safety check on the specific project before you pay anything.

Check a project free

Compiled from the MahaRERA public register. These are counts of the promoter's own legally-required disclosures — we describe the record, not the company. Possession dates are what the promoter declared, not a guarantee. Verify on maharera.maharashtra.gov.in.

Developers often register each project under a separate company, so one group may appear here under more than one name, and this page shows only the projects registered under “Ravi Developments”. How we compile this · Report a correction

Check a project