DOSTI ENTERPRISES

3 registered projects on our index, 1 completed with occupancy, 2 still within it.

Counted from the MahaRERA public register — not from the builder's own past-experience declaration. Earliest registration here is from 2017. Covers Thane — the districts indexed so far, so a builder active elsewhere may have more.

3

Registered projects

1

Completed with OC

0

Past declared date

0

Lapsed or flagged

Of the projects whose date has arrived

1 of 1 has completion recorded on MahaRERA. None are outstanding.

Size of the portfolio

1,311 homes across the projects indexed here, where unit counts are on record.

Have they kept to the dates they registered?

Across 3 projects with a declared possession date.

3
Date never pushed back
0
Pushed back up to a year
0
Pushed back over a year

MahaRERA publishes the date a promoter declared, not the date an occupancy certificate was issued — so this measures revisions to their own commitment, which is what the register can show.

Every registered project (3)

Looking at one of these?

A builder's record is context, not a verdict on the flat you're buying. Run the safety check on the specific project before you pay anything.

Check a project free

Compiled from the MahaRERA public register. These are counts of the promoter's own legally-required disclosures — we describe the record, not the company. Possession dates are what the promoter declared, not a guarantee. Verify on maharera.maharashtra.gov.in.

Developers often register each project under a separate company, so one group may appear here under more than one name, and this page shows only the projects registered under “DOSTI ENTERPRISES”. How we compile this · Report a correction