All projects

Marigold B wing

Shree Tirupati Greenfield Developers · Thane

RERA ID P51700004654

LapsedUpdated 17 Jun 2026
88
High risk

High delay risk — read the orders and talk to existing buyers before committing.

Key signals

RERA status
Lapsed
RERA registered
09 Aug 2017
Registered possession
30 Dec 2022
Revised possession
31 Dec 2025
Delayed by
3.5 yrs
Extensions
1
Overall construction
36%
Completion / Occupancy
CC ✓ (2) · OC ✗
Total units
87
Units sold
58 / 87 (67%)
Complaints filed
13
Litigation
3 case(s)

Construction status

36% overall
Excavation100%
Basement (if any)80%
Podiums (if any)0%
Plinth80%
Stilt Floor80%
Slabs of Super Structure41%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks10%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Commencement Certificates (2)

Multiple CCs on record — typically issued in phases as construction progressed.

  • Marigold CC.pdf28 Jul 2017
  • Marigold CC.pdf31 Jul 2018

Litigation (3)

  • High Court MumbaiCase 2695 · 2015Pending
  • Thane Civil CourtCase 1562 · 2012Disposed Of
  • Maharashtra Real Estate Appellate TribunalCase AT006000000052344 · 2020Pending

How the score is built

Transparent, additive factors from public data — total 88/100.

RERA registration status32 / 35

Registration has lapsed — a serious red flag.

Delay vs registered possession25 / 25

41 months past the originally registered possession date.

Construction progress10 / 15

36% complete.

Buyer complaints13 / 15

13 complaint(s) across 87 units (15%).

Order compliance0 / 10

No orders passed yet.

Litigation8 / 10

3 case(s) on record, 2 pending.

Orders passed

No orders on record for this project.

Complaints filed (13)

Hearing Scheduled8Order Approved4Bench Assigned1
View on MahaRERA ↗

Fetched live from MahaRERA: registration status, possession dates, units, promoter, construction progress and complaints. Formal orders aren't pulled yet. The Risk Score is an interpretive aid from factual public signals — not legal advice or a judgment on any promoter. Always verify on the official portal.