LODHA AMARA - TOWER 26, 27, 28, 30, 34, 35
LODHA DEVELOPERS LIMITED · Thane
RERA ID P51700001031
Some delay risk — watch the revised timeline and complaint trend closely.
What you can do
Key signals
Construction status
82% overallCommencement Certificates (2)
Multiple CCs on record — typically issued in phases as construction progressed.
- CC_100817.pdf19 Jan 2018
- Permission C C dated 20 01 2018.pdf30 Jan 2018
Litigation (2)
- Bombay High CourtCase 1737 · 2016Pre Admission
- Bombay High CourtCase 290 · 2016Pre Admission
How the score is built
Transparent, additive factors from public data — total 30/100.
Registration active and within timeline.
53 months past the originally registered possession date.
82% complete.
17 complaint(s) across 0 units (0%).
No orders passed yet.
2 case(s) on record, 0 pending.
Orders passed
No orders on record for this project.
Complaints filed (17)
Fetched live from MahaRERA: registration status, possession dates, units, promoter, construction progress and complaints. Formal orders aren't pulled yet. The Risk Score is an interpretive aid from factual public signals — not legal advice or a judgment on any promoter. Always verify on the official portal.